Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Agassiz teacher’s Amazing Race takes students on Canada-wide adventure

AESS students say they had the experience of a life time

WATCH: Brother of missing Hope woman makes emotional appeal for more media attention

Next search for Shawnee Inyallie Nov. 18 along Highway 1 towards Boston Bar

Gas price drop expected to hit Fraser Valley today

Analyst says to take advantage, warns slight increase may follow

Players Guild challenges Chilliwack residents to solve classic Agatha Christie whodunit mystery

The Chilliwack Players Guild is performing Murder on the Nile from Nov. 22 to Dec. 2

VIDEO: Stan Lee leaves posthumous message for his fans

Marvel Comics’ co-creator died on Monday at the age of 95

‘This is gangster,’ bait car thief declares on video

Footage from Abbotsford gains attention on social media

B.C. to fund gender-affirming surgeries for transgender people

Roughly 100 people in B.C. travel each year out of province for lower surgeries

U.S. mayor and dying dog’s roadtrip to B.C. goes viral

First vacation in three years came a month after blood cancer diagnosis

Federal fall update expected to offer more support for struggling news industry

Ottawa committed $50 million over five years for local journalism in ‘underserved communities’ last budget

UK’s May appeals to public on Brexit, braces for more blows

British Prime Minister Theresa May answered questions from callers on a radio phone-in, the day after she vowed to stay in office

UPDATED: $136M in transit funding coming to B.C.

The announcement was made at the BC Transit yard in Langford on Friday morning

Ottawa apologizes to Japanese family in B.C. after chopping historic cherry trees

Plaque installed in Prince Rupert to honour the memory of Shotaro Shimizu

Two B.C. police officers, held in Cuba for months, cleared of sex assault allegations

Port Moody Const. Jordan Long and Vancouver Const. Mark Simms have been in Cuba since March

Most Read