Port Mann Bridge review points to B.C. government’s flaws in expertise, risk management

Report takes aim at how the $3.3 billion mega-project was handled

The B.C. government needs to fix how it manages risk, timelines and documents before it undertakes another mega-project like the Port Mann bridge, an independent report has found.

The 174-page report, commissioned last year from Perrin, Thorau and Associates by the province, outlined seven broad recommendations arising from replacing the 1964-built bridge with a new, 10-lane crossing to address substantial congestion problems.

The report took aim at the province’s inability to assemble the “people, business processes and information systems” required to undertake a project of this size.

The province couldn’t properly manage risks throughout the project, the report said, and had trouble estimating the schedule, progress payments and performance measures.

Changes to the way the project was managed didn’t undergo a “competitive pricing test” to ensure they were getting the best value, it added, though the province didn’t keep proper records to determine if there had been an attempt to secure lower pricing.

READ MORE: Port Mann, Golden Ears traffic up since tolls removed: report

The $3.37-billion cost was $48 million over from the initial approval of $3.32 billion in 2009, after a public-private partnership was nixed following the global recession the year before. The government chose to took on debt and fully fund the project.

The consultants were “surprised by the extent to which the province was unable to recover key documents” in relation to that decision.

As costs increased, the report found that the province needed a better way to distribute contingency funding and revise how it estimates price markups that happen when a contractor has to change parts of the project.

The first drivers to use the new Port Mann crossed in September 2012.

Tolls, which took effect the following December, were expected to raise $175 million each year, but by 2015-16, a report from the bridge’s operator, the Transportation Investment Corporation, showed an annual operating loss at more than $100 million per year.

The finance ministry recently responded that it had already implemented the recommendations on projects undertaken since the Port Mann.

It pointed to the Evergreen Line and upcoming Pattullo Bridge replacement as examples of where a “independent cost estimator” is on-site to ensure better costing out of major projects, and said it was undertaking a review of its record management system.


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Just Posted

How much does your city spend per person on snow removal?

Black Press Media compares 2018 ice and snow removal budgets of various Lower Mainland communities

B.C. BUDGET: Surplus $374 million after bailouts of BC Hydro, ICBC

Growth projected stronger in 2020, Finance Minister Carole James says

UPDATE: Chilliwack man arrested for Agassiz break and enters

Westin Ferguson, 19, faces charges relating to break and enters throughout Agassiz

Short closures on Agassiz-Rosedale Bridge during pier upgrades

The project comes before the major retrofit of the bridge, which has been in the works since 2017

Preliminary inquiry starts for Chilliwack woman charged in 2016 fatal hit-and-run

Linnea Labbee, 70, accused in Dec. 1, 2016 incident that killed 78-year-old Fourghozaman Firoozian

VIDEO: Wheelchairs teach Agassiz students acceptance through sport

Teacher Donna Gallamore brought wheelchairs to the Kent Elementary for learning and fun

Market volatility, mortgages loom over upcoming earnings of Canada’s big banks

Central bank interest hikes have padded the banks’ net interest margins

Hearings into SNC-Lavalin affair start today, but not with Wilson-Raybould

She has repeatedly cited solicitor-client privilege to refuse all comment

VIDEO: 8 things you need to know about the 2019 B.C. budget

Surplus of $247 million with spending on children, affordability and infrastructure

Tilray to acquire hemp food company Manitoba Harvest for up to $419 million

Tilray will pay $150 million in cash and $127.5 million in stock.

Tears, flowers at impromptu memorial for Syrian children killed in Halifax fire

The family had only lived in the Quartz Drive home for a few months

NDP candidates push for stronger climate action as Singh supports LNG Canada

Singh has tried to project unity in the party while facing internal criticism for poor fundraising and low support in the polls

‘Bullet missed me by an inch’: Man recounts friend’s killing at Kamloops hotel

Penticton man witnessed Summerland resident Rex Gill’s murder in Kamloops

B.C. BUDGET: Income assistance raise still leaves many below poverty line

$50 per month increase included in funding for poverty and homelessness reduction

Most Read