Site C dam construction to start next summer

Province to take less revenue from BC Hydro to minimize its debt, says $8 billion project is the cheapest available option to meet demand

The B.C. government has given the go-ahead for BC Hydro to start construction on a third dam on the Peace River, with a delay of six months to try to work out settlements with area aboriginal communities and landowners whose properties will be flooded or cut off.

Energy Minister Bill Bennett said Tuesday an update of the construction costs upheld the $7.9 billion estimate for the Site C dam that was developed in 2010, but the estimate has risen.

Delaying the project six months from its original start date adds inflation and interest costs, and calculating the effect of the provincial sales tax replacing the HST bringing the total to $8.34 billion, and the province is establishing a “project reserve” of $440 million to bring the total estimated cost to $8.77 billion.

The project reserve is in case of unforeseen events such as a rise interest rates during the eight-year construction period.

BC Hydro CEO Jessica McDonald said the six-month delay provides time to work out agreements with Treaty 8 First Nations who have declined settlement offers. The federal-provincial environmental review panel gave the go-ahead for the project in May, but noted its unavoidable impacts on aboriginal hunting, fishing and trapping rights that are assured by the 1899 treaty.

A group of Peace valley landowners has already started legal action against the project, having refused offers from BC Hydro to buy their land. Aboriginal groups in Alberta, downstream of the project, have also started court action against it.

NDP leader John Horgan called the decision “a $9 billion gamble” and repeated his call for a review by the B.C. Utilities Commission to see if the additional power is going to be needed by the time the dam is operating in 2025.

The BCUC will determine BC Hydro rates in the years ahead, and how much they will go up to pay for the most expensive public construction project in B.C. history. The government plans to mitigate BC Hydro rate impact by reducing the dividend the government takes from the power company’s operations each year.

Bennett said a review of alternative clean energy sources, including wind, solar and geothermal power, showed they can’t compete on price because they are intermittent sources that would require backup power.

 

Just Posted

Village Classic Car show brings some muscle to Chilliwack’s downtown

Hot wheels and cool cars line Chilliwack streets

Serial killer Robert Pickton transferred to Quebec: victim’s family

Pickton was convicted in December 2007 of six counts of second degree murder

UPDATE: Fire destroys Chilliwack restaurant

Popular Banners Restaurant goes up in flames Sunday morning.

Moms of those killed by illicit opioids take to B.C. Legislature in call for action

Moms Stop the Harm, a nationwide network of families who have lost loved ones to overdoses rally

Man shot dead in Clayton area of Surrey, witnesses sought by police

It happened in the 18200-block of 67A Avenue

VIDEO: Agassiz Community Gardens turns 15

Growing is good for personal and community health

Man facing charges after baby food stolen from Richmond doorstep

A 40-year-old man is facing several charges

Man shot dead in Surrey ID’d as hockey coach and father of two

Murder of Paul Bennett – a respected Peace Arch Hospital worker and ‘champion of sport’ – ‘not random’

10 of TransLink’s most used SkyTrain routes

TransLink released its 2017 Transit Network Performance Review, offering snapshot of ridership

Serial speeder clocked going 138 km/hr in 90 zone

Driver had their vehicle impounded

Canadian Syrian children’s choir not to attend festival over fears about U.S. travel

Many kids are recent immigrants from countries covered by Trump travel ban

VIDEO: Plane crashes in Langley farm field (updated)

Plane lost power shortly after takeoff, RCMP told

Most Read