The Churchill Falls hydroelectric project under construction - file photo

Supreme Court sides with Hydro-Quebec in historic Churchill Falls dispute

It is one of Canada’s bitterest interprovincial feuds, the notorious 1969 Churchill Falls hydro deal between Quebec and Newfoundland and Labrador

The Supreme Court of Canada says there is no legal obligation to reopen the 1969 Churchill Falls energy deal that has been highly profitable for Hydro-Quebec but much less so for Newfoundland and Labrador.

In a 7-1 ruling today, the high court says it cannot force the parties to renegotiate the contract even though the arrangement has turned out to be unexpectedly lucrative for the Quebec utility.

Under the deal signed decades ago, Hydro-Quebec agreed to buy almost all the energy generated by the power plant on the Churchill River in Labrador.

The contract, covering 65 years, set a fixed price for the energy that would decrease over time. It’s earned more than $27.5 billion for Hydro-Quebec to date and about $2 billion for Newfoundland and Labrador.

Churchill Falls (Labrador) Corporation Ltd. went to Quebec Superior Court in 2010, arguing unsuccessfully that the sizable profits from electricity were unforeseen in 1969 and that Hydro-Quebec had a duty to renegotiate the contract.

An appeal court affirmed the ruling but the Supreme Court agreed to hear the corporation’s case.

In its ruling, the high court says that in Quebec civil law there is no legal basis for the claim advanced by the corporation, known as CFLCo, part of Newfoundland and Labrador Hydro.

A majority of the Supreme Court says CFLCo was seeking to undo certain aspects of the contract while keeping the ones that suit it. In effect, it was asking Hydro-Quebec to give up the benefits it obtained in exchange for the sacrifices it made to get the massive project up and running — a situation from which CFLCo has been benefiting since 1969 and continues to benefit today.

“Neither good faith nor equity justifies granting these requests,” the court says.

“In the final analysis, CFLCo has not provided any compelling factual or legal basis for the courts to reshape the contractual relationship it has had with Hydro-Quebec for the last 50 years.”

Related: Supreme Court of Canada won’t hear B.C. veterans’ lawsuit on pensions

Related: Supreme Court sides with Rogers in illegal movie downloading case

The landmark decision could have a profound influence on relations between Quebec and Newfoundland and Labrador, given long-standing tensions over the historic energy deal. The project, championed in the early days by then-Newfoundland premier Joey Smallwood, has long been a sore point.

The Churchill River in Labrador drops more than 300 metres over a stretch of less than 32 kilometres, making the falls one of the world’s most significant sources of hydroelectric power. A massive underground power station, carved out of solid granite, produces over 34 billion kilowatt-hours of energy annually.

In its submission to the Supreme Court, CFLCo said the energy market and regulatory landscape in 1969 were vastly different than they are today: energy was a public good with no real market value, and exports were simply a means of disposing of surpluses and required legislative authorization. Hydro-Quebec was a public service provider, required by law to sell to electricity to Quebec consumers at a low price.

Over the decades, everything has changed, CFLCo argued. Energy has become a supply-and-demand commodity with lucrative export markets.

In turn, Hydro-Quebec’s mandate evolved and the utility has made billions of dollars selling power to Quebecers and billions more exporting to previously non-existent markets at 20 to 40 times the contract price, CFLCo told the court. Meantime, the corporation remains stuck in 1969, with a fixed, declining electricity price.

Hydro-Quebec argued that under the contract it assumed the risk associated with any fluctuations in the market value of energy, which made financing the Churchill Falls project possible. In return, Hydro-Quebec had assurance that the price set in the contract would provide the utility, for the full term, with stable supply and protection against inflation.

In reality, CFLCo was seeking a new contractual balance bearing no relation to the original one struck by the parties — redress that falls outside the role and function of the courts, Hydro-Quebec said.

Though the project began generating power in the early 1970s, the contract formally took effect in 1976 with a 40-year term and an automatic 25-year extension — meaning it expires in September 2041.

In its ruling, the Supreme Court notes the terms of the contract will see CFLCo begin operating a plant worth more than $20 billion for its own benefit.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

5 to 10 cm of snow still coming to Fraser Valley: Environment Canada

Hard to say when the freezing rain will turn to regular rainfall, Environment Canada says

EDITORIAL: Honouring Kent’s history

Former editor Grace Kennedy reflects on the special edition for the 125th anniversary

Mount Woodside bike trail planning underway

With this week’s Council approval, planning can begin

FVRD WildSafe wraps up season

Black bears biggest source of calls in district

PHOTOS: Sts’Ailes students scale glaciers as part of mountain skills and wilderness program

‘It’s not just about taking kids hiking, it’s actually about connecting them to the land’

After cashing in on QB gambles, Chiefs and 49ers to clash in Super Bowl

KC beats Tennessee, San Francisco dispatches Green Bay to reach NFL title game

VIDEO: SPCA and RCMP remove several animals, including pig, at private animal rescue in Langley

Home at 5500 block of 216th Street has undergone multiple seizures over the past five years

B.C. VIEWS: Few clouds on Horgan’s horizon

Horgan’s biggest challenge in the remainder of his term will be to keep the economy humming along

Victoria family focuses on ‘letting go, enjoying time together’ after dad gets dementia

Walter Strauss has developed an interest in music and now takes line dancing classes

B.C. forest industry grasps for hope amid seven-month strike, shutdowns, changes

Some experts say this could be worse for forestry than the 2008 financial crisis

Northern B.C. RCMP investigating alleged sexual assault in downtown Smithers

One person was transported by ambulance to hospital following RCMP investigation at Sedaz

Vancouver police probe second homicide in less than 24 hours

Woman was found dead in her Gastown home

UBC, Iranian-Canadian community create memorial scholarship in honour of victims

The Jan. 8 crash killed 176 people, including 57 Canadians

Most Read